13 transformer stations in one week!
We undertook to unload, secure the substrates and drive the elements of 13 transformer stations! We planned the whole operation over 5 working days, delivered over 1,200m2 of temporary surfaces, 3 installation teams and two wheeled cranes with a lifting capacity of 60 and 100 tonnes. All stations arrived safely at the projected locations and were installed as planned!